We successfully launched the two largest projects this year..
The two photovoltaic power plants have installed capacity of more than 2 MWp.
Photovoltaic power in Tišnov (2 MWp)
- power of 2 MWp
- overall performance of the planned 2 000 kWp
- total land area of 50 340 m2
- usable area of 15 427 m2 of panels
- average energy of the incident solar radiation per year per 1 m2 of horizontal surface: 972 to 1040 MWh / year
- initiation of 09/2009
- completion of the 11/2009
More ...
and Hodonín (2.2 MWp)
- performance of 2.2 MWp
- total planned output 2 163 kW
- total area of land 45 940 m2
- usable area panels 15 149.5 m2
- average energy of the incident solar radiation per year per 1 m2 of horizontal surface: 972 to 1040 MWh / year
- initiation of 09/2009
- completion of the 11/2009
More ...
Among the projects are already running photovoltaic power plant in a Křižanov Popice. In accepts launched a photovoltaic power plant in Žeravinách.
Křižanov - photovoltaic power plant with output of 1 MWp.
- output 1 MWp
- overall performance of the planned 1 031 kWp
- total land area of 22 940 m2
- Panel 7 usable area 224 m2
- average energy of the incident solar radiation per year per 1 m2 of horizontal surface: 972 to 1040 MWh / year
- initiation of 05/2009
- completion of the 08/2009
More ...
Popice - photovoltaic power plant with output of 1 MWp.
- total land area of 19774 m2
- panels usable area 6418 m2
- average energy of the incident solar radiation per year per 1 m2 of horizontal surface: 972 to 1040 MWh / year
- initiation of 06/2009
- completion of the 09/2009
More ...
Žeraviny - photovoltaic power plant with 1.7 MWp.
- performance of 1.7 MWp
- overall performance of the planned 1 733 kWp
- total land area of 35 736 m2
- usable area of 12 260 m2 of panels
- average energy of the incident solar radiation per year per 1 m2 of horizontal surface: 972 to 1040 MWh / year
- initiation of 08/2009
- completion of the 10/2009